CityPlace Four

Project Summary

Building Four on the CityPlace campus was designed to attract technically-oriented tenants.  Fast tracking the design and construction allowed the building to be completed in eight months from inception of the design to construction completion.  Providing quality lease space for technology driven office tenants has been the constant, but each CityPlace office building project has introduced a new set of challenges. With CityPlace Four, the challenges included a tight, sloping site, connected parking garage, and master planning to include a future sister building.

Project Data

  • Creve Coeur, Missouri
  • The Koman Group
  • 103,000 sf
  • 4 stories